For multiplex builders, architects, and planners: see approval patterns by project type before you pay for drawings.
Email me the full report30,556
Applications matched to a lot
157
Areas with enough cases to compare
At least 10 decided cases
2022–2026
Approval trends shown
Covers applications since 2017. Area rankings use city lot-matched zones, not Toronto’s official neighbourhood boundaries.
Six project types, one chart each. Pick the lane that matches your build. No filters, no spreadsheets.
Fourplex & multiplex
Toronto’s multiplex policy shows up on COA dockets as four-unit and houseplex variances. Approval rates rose after 2023, but where you build still shapes the outcome.
In 2026, 79% of decided cases were approved (34 cases). Past results do not predict your outcome.
Approval rate by year
2022
92%
2023
100%
2024
82%
2025
83%
2026
79%
Areas with the highest approval rates
For minor variances, nearly all decided cases get an outcome the same day as the hearing. The slow part is getting on the docket: median wait from application to hearing is 85 days. Plan your timeline around queue time, not the hearing itself.
A minor variance lets one property depart from Zoning By-law 569-2013. The by-law stays in force for other properties. A rezoning is the application that changes the by-law. The findings, fees, and hearing steps below are the City’s, reviewed on 2026-10-08.
The City says the Committee must be satisfied that:
Those four findings restate Planning Act section 45(1). They are Toronto’s test. Other provinces use other names and other tests. Minor variance in Canada.
Minor variance application fees effective January 1, 2026. Chapter 441-4 of the Municipal Code adjusts them every January 1.
| Application | Fee |
|---|---|
| Additions and alterations to existing dwellings with 3 units or less | $2,228.98 |
| Residential dwellings with 3 units or less | $5,011.08 |
| All other residential, commercial, industrial, or institutional uses | $6,485.59 |
| After the fact variances | Double the regular fee |
The City’s procedure page does not state a scheduling target for minor variances. The wait from application to hearing on this page is Bucky’s, from Toronto open data.
Get the full report by email
We’ll send a PDF with all six project types, area highlights, and methodology, ready to forward to clients or partners.
Not legal advice. Historical Committee of Adjustment outcomes from public open data; past approval rates do not guarantee future results.
Data as of October 13, 2026.
Ready to see precedents on a specific lot? Book a demo and walk through your site with Bucky.